North End Neighborhood Drainage Project
 

WORK TO BE COMPLETED IN THE WEEK OF DEC. 24 TO 28

  • Feriozzi Concrete will finish work on Pleasure Avenue between Sixth Street and Seventh Street, as well as Sixth Street from Bay Avenue to the bulkhead. They will then begin work on the east side of Bay Avenue starting at Second Street.
  • Pipe crews will be installing 15" force main on 6th street from Bay ave to the bulkhead. A second crew will continue the installation of the pump station at 6th and Bay. 

  • South State will continue paving Wednesday, Dec. 26. They will be topping Third Street and Seventh Street from West to Bay, as well as Moore and Haven between 7th and 8th.
     
  • Arthur Henry will continue the installation of the bulkhead at Third Street. 